On 20 October this year, it is planned to complete renovation works on a 7-kilometre section of the Motorway in the direction of Łódź (km 2+200 to km 9+250) and to open the Kleszczewko MOP in the direction of Łódź.
Until mid-November, work will continue on a six-kilometre section of the Motorway towards Gdańsk (km 26+550 to km 20+460), where traffic runs in two lanes in the direction of Łódź and one lane in the direction of Gdańsk. In addition, vehicles heading towards Gdańsk will not be able to exit or enter at the Swarożyn junction. The completion of the works depends on weather conditions.
The speed limit on the renovated section is 80 km/h.
Drivers are asked to concentrate more closely and follow the signs of temporary traffic organization.
The graphic below shows the temporary traffic organization on the renovated section.